City begins demolition process of Somerset home damaged by landslide

Following an agreement between the City of Bellevue and a family whose home was irreparably damaged by a Jan. 17 mudslide in the Somerset neighborhood, the city has finalized a contract with a demolition contractor to remove the dangerous structure and salvage items where possible.

The first steps in preparation for demolition of the home owned by the Surdi family began on Feb 10.

The demolition of the home will remove an imminently dangerous hazard from the neighborhood and will allow nearby families to return to their homes that have been inaccessible since the slide due to the safety hazard.

Initial work began on the morning of Feb. 10, with demolition of the home expected to start Feb. 19. The entire demolition process, including prep, structure removal and debris removal, is expected to take several weeks.

“Our number one priority throughout this process is to keep people safe and to remove the dangerous structure as soon, and as safely, as possible,” said City Manager Brad Miyake. “We’re grateful to the Surdi family for allowing the demolition process to begin. I also want to reassure the community that the city is deeply committed to helping the Somerset neighborhood recover from this unimaginable event.”

Planned timeline of the process according to the city:

Feb. 10 – Preparation of the site begins

Feb. 14 – 18 – Roadway cleanup, site protection and equipment mobilization

Feb. 19 – 25 – Likely demolition dates and processing of debris

Feb. 28 – March 3 – Site stabilization, cleanup and demobilization

During demolition, the site will be secured and monitored for the safety of the public. Per the construction contract and the agreement with the homeowner, the contractor completing the work will remove and retain any vehicles on the site and seek opportunities to safely remove any salvageable items from the home, taking them to a safe location for the family to assess and collect. In addition, the Surdis will be able to observe the demolition activities from a safe location nearby during the work.

Meanwhile, the city says they will continue to engage daily with all impacted residents from the neighborhood and offer resources.

The investigation into the cause of the slide is ongoing and, due to the complexity of the incident, will take months to complete.

In consideration of how we voice our opinions in the modern world, we’ve closed comments on our websites. We value the opinions of our readers and we encourage you to keep the conversation going.

Please feel free to share your story tips by emailing [email protected].

To share your opinion for publication, submit a letter through our website https://www.bellevuereporter.com/submit-letter/. Include your name, address and daytime phone number. (We’ll only publish your name and hometown.) We reserve the right to edit letters, but if you keep yours to 300 words or less, we won’t ask you to shorten it.

Source: Bellevue Reporter